Installation
Installation Guide
In 5 steps you will reach your goal Step 1 Electrical installation Step 2 Connection to WLAN or LAN Step 3 Activation on floem. clemap.
Installation requirements
CLEMAP Load Management is used for dynamic power limitation of two or more electric charging stations in a garage or car park. The power consumption of the entire building is measured and the remaining available power for the charging stations is calculated and communicated in real time.
Step 1: Electrical installation
a. make sure that the power supply in the fuse box is disconnected.
Step 2: CLEMAP connection to a WIFI network or via Ethernet cable
Connect to the WiFi network created by the CLEMAP product with your smartphone or laptop. Log in with the following credentials.
Step 4: Integration of the charging stations, control and monitoring
On the portal https //floem. clemap.
Step 5 : Integration of ripple control signal from power supply company
CLEMAP Load Management supports external control signals, e. g.
Installation plans
Example installation plans can be downloaded from this page. The CLEMAP Load Management Gateway can interface with a Solar-Log Base paired with a Solar-Log PRO380.
FAQ Frequently asked question during installation
During installation, the CLEMAP product does not create a WIFI network with the name "clemapXX" The password for clemapXX WIFI network is not accepted I can’t reach floem. clemap.