title: Zaptec Pro, Home and GO
slug: help-center/zaptec-pro-home-and-go
docTags: 
createdAt: 2026-10-18T18:10:34.951Z
---

:::hint{type="info"}
**Prerequisites**

- The integration uses a cloud-to-cloud connection. An active internet connection of the Zaptec charging stations is mandatory.
- You need access to the **Zaptec Portal** and to **CLEMAP Load Management**.
:::

The setup is done in two parts: first in the **Zaptec Portal**, then in **CLEMAP Load Management**.

## Part A – Zaptec Portal

### 1. Configure power management

1. In the Zaptec Portal, open the relevant installation.
2. Navigate to **Settings → Power management**.
3. Enter the maximum circuit breaker values – marker **7** in the screenshot. Use the same value as the circuit protection you will enter in CLEMAP Load Management in step 4 (63 A in the example).
4. Enable **manual power control** – marker **8** in the screenshot.

![](https://api.archbee.com/api/optimize/N5BtsfQVOxPnQzfUQkalm/Hhpv6k8OfUgQQVyfpZLc8_zaptec-ladezeichen-installation.png)

:::hint{type="info"}
With manual power control enabled, CLEMAP Load Management takes over the dynamic allocation of the available current.
:::

### 2. Copy the installation ID

1. In the Zaptec Portal, go to the **Installations** tab.
2. Select the relevant installation.
3. Copy the **installation ID**.

::Image[]{src="https://api.archbee.com/api/optimize/N5BtsfQVOxPnQzfUQkalm/ycyUjFpPJnot6XNTZuyxj_computerbildschirm.png" size="80" isUploading="false" width="1335" height="1275" darkWidth="1335" darkHeight="1275" showCaption="false"}

## Part B – CLEMAP Load Management

### 3. Store the Zaptec credentials

Store your Zaptec credentials (username and password) in CLEMAP Load Management. Without these credentials, CLEMAP cannot communicate with the Zaptec cloud.

Detailed instructions: [Cloud-Anbieter Zugangsdaten](docId\:tDfBv491r81J8g01-5SPT)

### 4. Add the charging station

1. In CLEMAP Load Management, open the **EV charger setup**.
2. Select **Zaptec Pro** as the charging station. This selection also applies to **Zaptec Home** and **Zaptec GO**.
3. Paste the **installation ID** copied in step 2.
4. Enter the **circuit protection**. It must match the circuit breaker values from step 1 in the Zaptec Portal.

![](https://api.archbee.com/api/optimize/N5BtsfQVOxPnQzfUQkalm/OpuLvUEUx_0CDuTMk04r9_grafik.png)

:::BlockQuote
**Note:** Enter the protection of the **circuit**, not the limit of the individual charging station. In the example shown, the circuit is protected with 63 A and the main fuse with 125 A.
:::

:::hint{type="info"}
**Recommendation:** For Zaptec charging stations, set a **minimum current of 16 A** for the circuit in CLEMAP Load Management.
:::